Hi, I have problem, hope someone here can help me out...
While casting slab of Ground floor slab, We missed a portion of the slab as you can see the 'missing part' in the attached picture, There is no steel going out except for stairs reinforcement from from GF to FF.
Horizontal Beam reinforcement is 10T16 bar at bottom and 10T12 Bar at top..
This missing Part is 90cm.

Can anyone help me how to sort this out? How to cast this portion? Chipping up to 15-20cm and connecting with the HB reinforcement will sort it out?
NEED HELP...