Read Engineering360 article: Quality Defects Will Delay This Nuclear Unit's Startup.

Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru

Join Date: Apr 2011
Posts: 8006
Good Answers: 286
#1

Re: Quality Defects Will Delay This Nuclear Unit's Startup

07/26/2018 9:30 PM

"... The utility went on to inspect 150 welds..."

...which resulted in more than 1/3 being slated to be redone.

That is a very high rate of unacceptable work. Problems with welds should be caught and corrected as the fabrication is progressing. It seems like this could be indicative of more widespread problems.

I doubt there are only 150 welds in the entire primary and secondary. Those also aren't likely to be the only place where weld quality is of critical importance.

Sounds like further inspection might be called for.