In power stations the generator is connected to grid through power transformers. the power transformers have connections like YNd1 or YNd11 or Dyn1. what is the criteria for selecting a particular connection symbol?
You can read through this i think you will find all want in it.
Segun Nig
transformer vector group
Jul 4, 2005 8:58 pm, by krishna Subject : Engineering from the Automation List dept. Text :
why we need to specify the transformer vector group in substation design. If the vector grp of a generating transformer is changed from yd11 to yd1 how it will be going to affect in synchronising the generator
There had been a detailed discussion on & were more than 40 postings:
transformer:
http://globalspec.ip09.com/rd/9z1zeqi01ahsv1893bacrpd6q15dbnoje18oee6r01g