Previous in Forum: Open for Remote Structural Engineering Collaboration   Next in Forum: Ensuring Data Accuracy and Integrity for Microsoft MB-820 Exam
Close
Close
Close
Rate Comments: Nested
Participant

Join Date: Dec 2025
Posts: 2

Question About Cost Planning for Industrial Steel Structures

12/19/2025 2:21 AM

I am working on an industrial building project and would like to ask how engineers here approach early cost planning for steel frame structures. In many projects, design changes happen often, so estimating weight, connections, and fabrication cost becomes difficult. Do you usually base calculations on past project data, or do you use preliminary takeoff methods during concept stage? I am also interested how you manage coordination between structural design and budgeting, especially when preparing a steel structure estimate for bidding or feasibility review. Any advice or shared experience from engineers or project managers will be very helpful. Thank you.

Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Power-User

Join Date: Jul 2017
Posts: 236
Good Answers: 9
#1

Re: Question About Cost Planning for Industrial Steel Structures

12/20/2025 9:53 AM

Hi Alyana, even though I do no work in the construction industry, the estimating methods are basically similar, only the materials and weights change.
I start with the original Request for Quotation from the customer which usually gives the basic details of what he wants.
Depending on what support from Design, (if any) and, naturally, your own degree of expertise, you can generally work out what the dimensions are, how long is the building, how wide, how high to roof level, How high are the steel trusses, how many uprights are needed etc.
Are the uprights & Crossmembers just supporting the roof or is there a need for an overhead crane ?
Once you have worked out roughly how much steel you need, H-section or L section for Roof trusses, Cross braces etc. do a rough estimate detailing on what your estimate is based, how many running meters, what section you used.
Any other costs for secondary work, drilling and bolts or welded joints. Additional costs for cranes and other equipment like weldingmachines. manpower etc.
This is your first basic estimate, do not ever change it or amend it.
Any subsequent changes must be detailed with regard to what changed from the previous estimate and the subsequent costs added (rarely subtracted ) from the previous estimate.
Always use a suffix to your estimate with a date, that way you can always go back and say that Design / Material / Assembly changed and cost x amount. Traceability, record who requested the change and who signed off on it !!
Always make sure everybody involved in the Offer / Bid is informed about any changesto Design / Cost.
That shows accountability, so nobody can come later and say you didn't tell us about the changes or the cost implications

Register to Reply
Register to Reply

Previous in Forum: Open for Remote Structural Engineering Collaboration   Next in Forum: Ensuring Data Accuracy and Integrity for Microsoft MB-820 Exam

Advertisement