work execution plan/strategy to retube high pressure boiler

08/04/2008 11:03 AM

we are to repair a high pressure boiler; i need a work execution plan for retubing of this high pressure boiler

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Anonymous Poster
#1

Re: work execution plan/strategy to retube high pressure boiler

08/04/2008 4:25 PM

WOW!!!! That is quite the question ...............

I don 't have the time to give a complete answer, HOWEVER .........

Please be sure to hydrotest the boiler upon completion

Reply
Anonymous Poster
#2
In reply to #1

Re: work execution plan/strategy to retube high pressure boiler

08/04/2008 4:50 PM

Alright, I have a little time to provide and hopefully steer you in the right direction-

It seems from your question that you are lacking the most basic/fundamental knowledge regarding boiler repairs. My first piece of advice would be to hire a competent engineer/consultant/contractor to help you with this endeavor.

Apart from that - you must first specify what type of boiler, pressure rating, and size.

From there the issues you must address include:

  1. Applicable code to which boiler was manufactured/to be repaired (for example to AMSE BPVC Sec 1)
  2. Safety issues including vessel isolation/lock-out and if confined space entries must be done
  3. Proper materials for the replacement tubes (see applicable code) and proper certification for these materials
  4. Proper qualified workers/contractors (for example certified to National Board 'R')
  5. Proper welding procedures (dependent on materials and design)
  6. Proper heat treating of weldments (pre/post heat)
  7. Inspection/NDT of all repairs (including, but not limited to MPI/LPI, and X-ray requirements)
  8. Proper documentation of all repairs (including, but not limited to mill certs for materials, welding procedures, welder qualification card records, NDT results)
  9. Finally a hydrotest of the boiler (typically at 1.5 x design pressure) to ensure repairs are sound

Hopefully this provides a little insight into your predicament.

Reply
Active Contributor
India - Member - Gandhigiri

Join Date: Jan 2007
Posts: 13
#3

Re: work execution plan/strategy to retube high pressure boiler

08/15/2008 10:39 AM

you have to contact boiler manufacturer.

Reply
Anonymous Poster
#4

Re: work execution plan/strategy to retube high pressure boiler

10/09/2009 9:54 AM

Recommend that you contact the following company - www.limburns.co.uk

Reply