Previous in Forum: surface roughness   Next in Forum: Insulation of Valves and Flanges in Hydrocarbon and Hot Oil Lines
Close
Close
Close
8 comments
Rate Comments: Nested
Associate

Join Date: Dec 2008
Location: Tamilnadu,India
Posts: 26

Welding and ASME Standards

05/31/2009 1:01 PM

Interpretation of penalty for welders:

For sample,

1)welder did the welding 100 joints.Random RT 5% done on for 100 joints(RT-5joints).No defect found.so welder is pass.

2)The same welder did next (second)100 joints.Welder is pass on progessive sampling as mentioned above.

3)The same welder did next(third)100 joints.Welder failed during the progressive sampling test.so welder is disqualified.

The question is repairing to be done either third 100 joints only or 300 joints(sum of first,second and third) as per asme b 31.3 341.3.4

__________________
Love to learn
Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Power-User

Join Date: Jan 2009
Location: Western Canada
Posts: 295
Good Answers: 51
#1

Re: penalty interpretation of asme b 31.3 sec 341.3.4

05/31/2009 2:51 PM

Neither. 100% of the given lot size are only required to be redone on after the third repair/failure. You need to specify how many welds failed in your #3. (By the way the min. requirements of B31.3 would not disqualify the welder, only the welds - to completely disqualify the welder would be up to the owner/design spec)

Upon failure of subsequent testing in your #3 lot the answer would depend:

  1. What is the actual lot size specified? (100, 300, ...?)
  2. What is the total number of welds in the entire system?
  3. What is specified by the engineering design?

The purpose of progressive sampling is to provide a means to detect problems and rectify them before the entire piping system is completed. The 100% rework rule is to allow this before the system is done and has to be completely reworked. (eg. a matter of redoing 100 welds versus 500)

__________________
A little knowledge is a dangerous thing.
Register to Reply Score 1 for Good Answer
Anonymous Poster
#4
In reply to #1

Re: penalty interpretation of asme b 31.3 sec 341.3.4

06/01/2009 12:05 PM

does anybody else experience a bad link for the image linked above?

right-click and "Save Target As" results in an 88 byte "non-image" as well...

Register to Reply
Power-User

Join Date: Jan 2009
Location: Western Canada
Posts: 295
Good Answers: 51
#6
In reply to #4

Re: penalty interpretation of asme b 31.3 sec 341.3.4

06/01/2009 4:08 PM

I don't have a problem from my work computer (was uploaded from home) - if more people post saying there are issues I can resubmit it when I get home again.

__________________
A little knowledge is a dangerous thing.
Register to Reply
Associate

Join Date: Dec 2008
Location: Tamilnadu,India
Posts: 26
#7
In reply to #1

Re: penalty interpretation of asme b 31.3 sec 341.3.4

06/04/2009 1:56 PM

Thank you sir.

I have seen a flow chart. I have some doubt that in flow chart is following,

1)Lot means whether it should be same kind of piping material classes or it may be different classes

2)Whether i can consider this flow sheet progressive sampling applicable for piping material class basis and/or welder basis.

Waiting for your reply with thanks

__________________
Love to learn
Register to Reply
Power-User

Join Date: Jan 2009
Location: Western Canada
Posts: 295
Good Answers: 51
#8
In reply to #7

Re: penalty interpretation of asme b 31.3 sec 341.3.4

06/05/2009 1:11 AM

The code is pretty vague regarding this except for "each welder's and welding operator's work shall be represented".

It is left up to the owner/engineering design to prescribe a lot size and extent.

Take a hypothetical situation (and in my opinion, what I would do):

*******************

Installation of a new heat exchanger and associated piping (shell in/out, tubes in/out)

Shell side is cooling water, class 150 flanges, STD wall carbon steel; tube side is process gas, class 600 flanges, XS wall stainless steel.

Both are specified as normal fluid service, but with a 10% random RT on circ welds (which is above and beyond code min of 5% random RT on circ welds)

Both the shellside in/out & tubeside in/out each have (coincidentally) 100 welds each.

One would specify separate lots for each - which makes sense - you have different materials, different welding procedures, and different classes.

Shellside:

  • 2 welders - each do 50% of welds, ie. 50 welds each
  • 10% RT will require 10 welds in total, it would be prudent to split equally so that 5 welds of welder A and 5 welds of welder B are examined.

Tubeside:

  • 11 welders - each do approx. 9 welds.
  • HOWEVER, as mentioned above you need to include (represent) each welder.
  • Therefore, you would need to, AT A MINIMUM, examine 11 welds (1 from each welder), which works out to 11% RT, but that is the way it has to be.
__________________
A little knowledge is a dangerous thing.
Register to Reply Score 1 for Good Answer
Associate

Join Date: Mar 2009
Posts: 46
#2

Re: penalty interpretation of asme b 31.3 sec 341.3.4

06/01/2009 1:11 AM

Mr Rajan, before anything you have to designate the lot to be (NDT) Tested. I had obtain easy results using LOTS no more than 20 welds. (For same welder, same process .......), dayly production could be also considerate a lot, but is no a good control. Please review ASME B31.3 point 344.1.3 foot note 2.

Register to Reply
Guru
Hobbies - DIY Welding - pipewelder

Join Date: Apr 2007
Location: North Georgia, USA
Posts: 671
Good Answers: 33
#3

Re: Penalty Interpretation of ASME b 31.3 sec 341.3.4

06/01/2009 9:08 AM

The rule I use is 3 strikes you are out. No matter how many welds a welder has made on the third repair he loses his job. If I pay for 100% welds I expect 100 % because a weld repair is not a chance thing that can't be avoided as some would think. If a welder is worth a darn he knows what will pass and what won't and he knows how to fix a bad spot as he makes the weld.

__________________
pipewelder
Register to Reply
Guru

Join Date: Dec 2005
Location: Wisconsin USA
Posts: 824
Good Answers: 37
#5
In reply to #3

Re: Penalty Interpretation of ASME b 31.3 sec 341.3.4

06/01/2009 12:15 PM

"The rule I use is 3 strikes you are out." But the OP says (for the first 100) "No defects found." The wording is unclear, but it SEEMS to say that none were found on the second 100 pieces, either, since the welder passed. How does the coincidence of the first failure happening during the third group inspected, plus a baseball rule [though in recent years copied over into felony laws in some places], lead to this?

I do agree that a good welder should know what is acceptable and what is not, be watching while working, and self-correcting. If the issue is that the welder has decided to see how poor a job he/she can get by with, there is an entirely different basis for dismissal, IMHO.

__________________
" Ignorance and arrogance have more in common than their last four letters. "
Register to Reply Off Topic (Score 5)
Register to Reply 8 comments

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Copy to Clipboard

Users who posted comments:

Anonymous Poster (1); atorroja (1); pipewelder (1); rajan_balans (1); Ron (1); XMech (3)

Previous in Forum: surface roughness   Next in Forum: Insulation of Valves and Flanges in Hydrocarbon and Hot Oil Lines

Advertisement