There seems to be no commonly acceptable standard/or practice on the test voltage and the duration for the hipot tests on the HV cables.
For example,for a 33KV cable commissioning test after laying,DC voltage of 67KV dc (twice the system voltage + 1 kv) for 15 mts.is in vogue in INDIA.
Engineers now opine that this is not safe for the cable,1 mt. or 5 mts duration is ideal.
Better still is to test the cable with a VLF (very low frequency such as 0.1 H etc) at a
much lower volt and shorter duration than DC hipot test.
Specialists' recommendation with proof of authority when in dispute will be very helpful
to the community.