Why the expansion is more at IP turbine in thermal power plant compared to other (HP and LP) turbines ??????

Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru
Engineering Fields - Power Engineering - New Member

Join Date: May 2007
Location: NYC metropolitan area.
Posts: 3230
Good Answers: 444
#1

Re: Expansion at IP Turbine

09/14/2011 3:00 PM

Good interview trick question. Answer is that it is not a generalization but instead a function of the overall design of the steam cycle at the plant. For example if this were in an extraction cycle the IP turbine might be designed to provide (extract) process steam to a refinery and less work to the turbine shaft.

__________________
“Tell me and I forget. Teach me and I remember. Involve me and I learn.” Ben Franklin.
Register to Reply
Active Contributor

Join Date: Feb 2010
Posts: 10
#2
In reply to #1

Re: Expansion at IP Turbine

09/14/2011 11:37 PM

thank u sir...... still iam in a confusion....can u provide little bit more info

Register to Reply
Guru
Engineering Fields - Power Engineering - New Member

Join Date: May 2007
Location: NYC metropolitan area.
Posts: 3230
Good Answers: 444
#3
In reply to #2

Re: Expansion at IP Turbine

09/15/2011 2:34 PM

It is part of the overall design philosophy of the power plant and is subject to the usual considerations of cost, fuel, local conditions, etc. The designer of the power plant decides how to maximize the amount of energy that can be taken from the fuel and steam flow based upon his customer's requirements.

Here's one link

http://library.thinkquest.org/C006011/english/sites/dampfturbine.php3?v=2

There's plenty more on Google...

__________________
“Tell me and I forget. Teach me and I remember. Involve me and I learn.” Ben Franklin.
Register to Reply
Active Contributor

Join Date: Feb 2010
Posts: 10
#4
In reply to #3

Re: Expansion at IP Turbine

09/16/2011 3:06 AM

thank u sir.....