Hi all,
since, i am serving as a electrical contractor for Petrol fueling stations, we are following unloading(product unload from tanker to underground storage tanks) earthing as follows:
All metal parts(unloading pipe and tanker lorry) have interconnected.
All metal bodies (both unloading pipe and tanker lorry) connected individualy to dedicated earthpits.
I want to know this procedure is OK, if not any better suggestion.