Hello everybody:

As a matter of fact, for hydropower plants, the efficiency of its turbines is measured at the start of operation and, eventually, at regular intervals.

Through the time, two basic types of turbine testing, the absolute and the relative, have been customary.

Even when I understand the principles and differences between them both, I would like to know your comments regarding with:

The absolute methods are more complex, expensive and difficult and are generally done once, to ensure the contract guarantees have been met.

The relative efficiency testing (Index Testing) is considerably easier, determines the relative performance of the entire turbine-generator unit and is a complete on-site system evaluation.

For a particular case, turbines of around 8 MW each, under what premises it is chosen one test or the other?

Can it be used, in a reliable basis, the relative method as a substitute of the absolute method?

Your comments are welcome. Thanks.

Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru

Join Date: Mar 2007
Location: by the beach in Florida
Posts: 33392
Good Answers: 1817
#1

Re: Efficiency tests of Hydraulic Turbines

08/14/2013 12:55 PM
__________________
All living things seek to control their own destiny....this is the purpose of life
Register to Reply
Commentator

Join Date: Sep 2006
Posts: 64
#2

Re: Efficiency Tests of Hydraulic Turbines

08/15/2013 6:08 PM

Hello everybody:

SolarEagle, thanks for your nice gesture providing this document.