Hi i had a problem regarding the 380kv substation TEE protection CTs. We are using 6 CT method(of different cores) for Tee protection in one and half breaker scheme. My doubt is for which CT is specific for what protection and another 2 core CT were installed outside the GIS and what is significance of those 2 core CT.