Dear Sirs,

What are the various steps in the construction of a Gas Insulated Substation in an area?

(eg. soil testing, foundation design, resistivity testing, grounding system design etc.)

Best Regards,

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Guru

Join Date: Oct 2008
Posts: 42355
Good Answers: 1693
#1

Re: Substation Construction Works.

07/15/2018 2:38 PM
Reply Score 1 for Good Answer
Guru

Join Date: Oct 2014
Location: Hemet, Land of milk and honey.
Posts: 2365
Good Answers: 36
#3
In reply to #1

Re: Substation Construction Works.

07/15/2018 10:55 PM

Did I say two, I meant three.

Reply
Guru
Engineering Fields - Power Engineering - New Member

Join Date: May 2007
Location: NYC metropolitan area.
Posts: 3230
Good Answers: 444
#2

Re: Substation Construction Works.

07/15/2018 3:44 PM

The first step is to contact the various vendors of GIS equipment, they will guide you through the process.

__________________
“Tell me and I forget. Teach me and I remember. Involve me and I learn.” Ben Franklin.
Reply
Anonymous Poster #2
#4

Re: Substation Construction Works.

07/16/2018 2:54 AM

Read here.

Reply
Guru
United Kingdom - Member - Indeterminate Engineering Fields - Control Engineering - New Member

Join Date: Jan 2007
Location: In the bothy, 7 chains down the line from Dodman's Lane level crossing, in the nation formerly known as Great Britain. Kettle's on.
Posts: 32175
Good Answers: 839
#5

Re: Substation Construction Works.

07/16/2018 2:55 AM

Ah! That's an easy one to answer: they can be found on the design documents for the previous one.

__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Reply
Anonymous Poster #3
#6

Re: Substation Construction Works.

07/16/2018 7:04 AM

Without the correct volume of Carbonarro you could not possible insulate the substation with gas. How will you get the feeders in and the outgoing feeders out if the sub in the middle is insulated?

Is this a trick question?

Reply
Anonymous Poster #2
#7

Re: Substation Construction Works.

07/16/2018 8:28 AM

Is there a prize for getting this right?

Reply
Guru
United Kingdom - Member - Indeterminate Engineering Fields - Control Engineering - New Member

Join Date: Jan 2007
Location: In the bothy, 7 chains down the line from Dodman's Lane level crossing, in the nation formerly known as Great Britain. Kettle's on.
Posts: 32175
Good Answers: 839
#8

Re: Substation Construction Works

07/17/2018 8:25 AM

<...Gas Insulated...>

All gases are insulators.

__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Reply
Guru
Engineering Fields - Power Engineering - New Member

Join Date: May 2007
Location: NYC metropolitan area.
Posts: 3230
Good Answers: 444
#9
In reply to #8

Re: Substation Construction Works

07/17/2018 9:54 AM

Really? I guess you've never seen a neon sign!

__________________
“Tell me and I forget. Teach me and I remember. Involve me and I learn.” Ben Franklin.
Reply
Reply to Forum Thread 9 comments

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Copy to Clipboard

Users who posted comments:

Anonymous Poster (3); lyn (1); PWSlack (2); RAMConsult (2); tonyhemet (1)

Previous in Forum: Broken Wire Analysis   Next in Forum: Soil Resistivity Testing of Transmission Line

Advertisement