Hydro Testing of Air Receiver Tanks.

05/23/2008 1:40 AM

What is the minimum time duration to be maintained for Hydro testing Air receiver tanks? . Is there any relationship between the capacity of the tank and the time duration of the hydro test?

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru
United Kingdom - Member - Indeterminate Engineering Fields - Control Engineering - New Member

Join Date: Jan 2007
Location: In the bothy, 7 chains down the line from Dodman's Lane level crossing, in the nation formerly known as Great Britain. Kettle's on.
Posts: 32175
Good Answers: 839
#1

Re: Hydro Testing of Air receiver tanks.

05/23/2008 4:44 AM

The insurance inspector/surveyor's report shedule will give guidance. In the UK, pressure systems must have a written scheme of examination, and this item is best discussed with the relevant insurance company.

__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Reply
Anonymous Poster
#2
In reply to #1

Re: Hydro Testing of Air receiver tanks.

05/24/2008 4:49 AM

As a french Inspector, I'm familiar with this Hydro procedure i,n France. The duration of this test is not clearly defined by the Standards. In practice, all factories used to take 30 min. In effect, if any leak was to occur, it should occur immediately orwithin a few minutes after starting.

Reply
Anonymous Poster
#3

Re: Hydro Testing of Air Receiver Tanks.

05/24/2008 2:11 PM

My 1st answer was directed to guest N°1. Anyway, to complete my answer, the duration of the Hydro Testing is not related to the capacity of the tank. Nevertheles, some Engineering Cy may ask for One hour testing (it happenned to me). The reason was because the tank was a spiral heat exchanger of 20 tons and the inner metal sheets were withstanding a lot of fatigue. Note that with one hour instead of 30 min, the fatigue is increasing. The soldering of those sheets were working hard (we can hear the crack sound) and could have broken slightly as small cricks. This hydro test is always followen by an air (or nitrogen) pressure test to confirm NO leakage.

Reply
Guru
Spain - Member - New Member Engineering Fields - Nuclear Engineering - New Member

Join Date: Oct 2007
Location: Madrid, Spain
Posts: 716
Good Answers: 25
#4

Re: Hydro Testing of Air Receiver Tanks.

05/25/2008 11:16 AM

I don't know any code or standard which relates the test pressure with the tank volume.

But hydrostatic (or pneumatic) testing are usually ruled by the design code and the local laws. According to what code are the tanks constructed? Have a look on it and surely you'll find the requirements on pressure level and minimum time at pressure.

Best regards

__________________
It's stupid to discuss about AI: We´ve reached by the "B" way. We' ve producing men as clever as machines.
Reply
Active Contributor

Join Date: Mar 2008
Posts: 15
Good Answers: 2
#5

Re: Hydro Testing of Air Receiver Tanks.

05/27/2008 12:06 PM

First question is where are you located on the planet? Different countries, different codes in most cases.

Second question being what is the application and will it be transported over the road or stationary?

United States has Department of Transportation codes applicable to containers and vessels transported over the road.

Reply
Reply to Forum Thread 5 comments
Copy to Clipboard

Users who posted comments:

Anonymous Poster (2); handyman242 (1); Kwetz (1); PWSlack (1)

Previous in Forum: compressed air challenge   Next in Forum: Centrifugal force

Advertisement