Regarding calculation:

08/07/2008 9:06 AM

Dear Sir,

Pl. send the details of Incoming Power Cables ( Al.) for below mentioned Star / Delta and DOL Starters.

1.100 KW De-watering pump Star / Delta Starter

2.50 KW Drainage pump Star / Delta Starter

3.25 KW Cooling Water pump Star / Delta Starter

4.25 KW Compressor Air System Starv / Delta Starter

5.25 KW Oil pump DOL Starter

6.25 KW Oil pump DOL Starter

7.10 KW Oil pump DOL Starter

8.3.7 KW DOL Starter Oil pump

9.3.7 KW Oil pump DOL Starter

10.3.7 KW Vacuum Cleaner Pump DOL Starter

11.1.5 KW Grease Pump DOL Starter

Thanking you sir,

Yours faithfully,

Kishore,

09985376488.

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru
United Kingdom - Member - Indeterminate Engineering Fields - Control Engineering - New Member

Join Date: Jan 2007
Location: In the bothy, 7 chains down the line from Dodman's Lane level crossing, in the nation formerly known as Great Britain. Kettle's on.
Posts: 32175
Good Answers: 839
#1

Re: Regarding calculation:

08/07/2008 9:18 AM

This is an engineering news and discussion forum.

The local project cable installer can refer to the project cable schedule for this information. The cable schedule will be found within the contract design documents.

__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Reply
Guru
Canada - Member - If there is a way to screw someting up, there is someone to do so! Safety - Hazmat - New Member

Join Date: Mar 2007
Location: Iqaluit, NU. Canada
Posts: 1854
Good Answers: 140
#2

Re: Regarding calculation:

08/07/2008 5:37 PM

Two things...

1) You want some one to do your work for you, and...

2) You really want some one to do your work for you.

__________________
Joe Contractor to Electrical Inspector, "What do you mean you are going to make me follow the code?".
Reply
Associate

Join Date: Jul 2006
Location: OZ
Posts: 33
Good Answers: 3
#3

Re: Regarding calculation:

08/08/2008 2:30 AM

We need to know the working voltage between phases

__________________
Shocking from OZ
Reply
Reply to Forum Thread 3 comments
Copy to Clipboard

Users who posted comments:

nap (1); North of 60 (1); PWSlack (1)

Previous in Forum: SMPS   Next in Forum: Earth fault relay operation (in detail )...

Advertisement