Hi everyone.!Rehabilitation of ambuklao dam is ongoing and by March or April, the new generartors might be installed. The contractor will be conducting generator capability test very soon w/c includes

a. reactive power test

b. primary response test

c. fast start capability

d. black start

e. declared data capability

f. dispacth accuracy

Anyone could define and give a short step in this kind of tests.?Much thanks to everyone who could help.Godbless

KInd regards,

carel

__________________
every second counts in our life...
Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Anonymous Poster
#1

Re: generator capability test

01/07/2010 5:55 AM

What is the used of your internet? Go browsing in each you want to know...

Register to Reply
Guru
United Kingdom - Member - Indeterminate Engineering Fields - Control Engineering - New Member

Join Date: Jan 2007
Location: In the bothy, 7 chains down the line from Dodman's Lane level crossing, in the nation formerly known as Great Britain. Kettle's on.
Posts: 32175
Good Answers: 839
#2

Re: generator capability test

01/07/2010 7:18 AM

The tests need to have been defined at order placement stage.

If they haven't, ask the contractor to provide a statement of the testing, together with "pass"/"improvement required" criteria, for review and assessment.

__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Register to Reply
Register to Reply 2 comments

Previous in Forum: iso later quarries   Next in Forum: Identifying the Transformer

Advertisement