Earthmat in Switchyard

08/22/2010 4:15 PM

IN 132 KV SWITCHYARD WHICH MATERIAL SHOULD BE TAKEN MS ROUND BARS AND GI STRIPS FOR EARTHMAT AND WHY?

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru

Join Date: Oct 2009
Posts: 2061
Good Answers: 169
#1

Re: Earthmat in Switchyard

08/24/2010 5:52 AM

Please refer to IEEE 80.

Any material can be used. Only the material constants during thermal sizing would vary depending upon the material. Between MS & GI due allowance should be given for corrosion too.