Previous in Forum: How to Prevent Stroboscopic Effect   Next in Forum: Electrical Power Cables Laying
Close
Close
Close
Rate Comments: Nested
Anonymous Poster

GIS-SF6 230 KV Switchgear Bus-Bar Protection

11/21/2010 11:42 PM

We are now upgrading out 230 kv SF6 Switch gear bas-bar protection system. This needs to replace the existing protection panels with new one at the same place. Contractor has submitted the schedule indicating that at least for 2 months 230 kv switch gear bus-bar differential protection and breaker failure protection need to be bypaased to carry out the up-grading. After bypassing he will disconnect the existing wiring from each bay and loop to the new panel. Our plant has 9 TG sets (140*5 & 120*4 mw gen) connected to two bus-bars and four export lines, with bus-coupler. I would like to know, Is it allowed to run the plant with above protections bypassed?. If not, what is the alternate solution?. In other plants How they are doing this up-grading project? Who is the authority to approve the protection bypassing - Plant manager or grid controller? Expecting your suggestions and advice in this regard, Thank you.

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Guru
United States - Member - Member Engineering Fields - Electrical Engineering - Electrical Construction

Join Date: Apr 2010
Location: Mid Western USA - The Corn Belt
Posts: 1439
Good Answers: 58
#1

Re: GIS-SF6 230 KV Switchgear Bus-Bar Protection

11/22/2010 11:48 AM

It would be very un-advisable and in the plants that I work would be out of the question (not allowed) to bypass any protection system for even two seconds.

We are in the process of installing new switchgear at a local power plant to replace existing switchgear installed in 1968.

This replacement will take place during a 6 day "outage" in which we will run three shifts to accomplish this work.

"Outage" meaning the plant will stop producing and related, buss, panels, ect. will be locked out and made safe to accommodate the installation of the new gear.

During the "outage" other maintenance (electrical and mechanical) will be performed.

The plants that I work, depending on the facility, if power can not be re-routed through another buss (by means of a tie switch or similar) an outage is required for this work.

This is the only way to ensure safety of personnel and protection of equipment.

__________________
The first 5 days after a weekend are always the hardest................................
Reply Score 1 for Good Answer
Reply to Forum Thread

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!

Previous in Forum: How to Prevent Stroboscopic Effect   Next in Forum: Electrical Power Cables Laying

Advertisement