01/20/2011 4:59 AM

if joint design change in welding , what is requirement

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Anonymous Poster
#1

Re: wps

01/20/2011 5:30 AM

Cut the weld with the help of gas cutter and gring the given edges with grinder and then weld it back

Reply
Guru

Join Date: Jan 2010
Location: Mineral wells Tx
Posts: 630
Good Answers: 34
#2

Re: WPS Question

01/20/2011 11:41 AM

For most of the welding process, the desing of the joint is Nonessential . Check ASME IX, QW- 250

Reply
Commentator
United States - Member - Member Engineering Fields - Manufacturing Engineering - Member Hobbies - Fishing - Member

Join Date: Jun 2008
Location: Somewhere in Nebraska
Posts: 93
Good Answers: 2
#3

Re: WPS Question

02/25/2011 3:02 PM

As long as the joint is still an AWS pre-qualified weld, you can weld as required in the WPS. If it is outside of the pre-qualified parameters, the weld must be qualified with approved AWS testing (Found in AWS D1.1 / D1.3, etc. if compliance to AWS is required). I believe API compliance criteria is similar.

__________________
"Stepping up to the plate" is not enough, you have to swing to get a hit!
Reply
Reply to Forum Thread 3 comments
Copy to Clipboard

Users who posted comments:

Anonymous Poster (1); Camilliontwo1 (1); Whitephone (1)

Previous in Forum: New WPS or PQR is Required   Next in Forum: Coal Tar

Advertisement