hi,

can anybody explain the logic or principle behind these measurement 1 out of 2 and 2 out of 3 logic? why is it called so? what would happen in 1 of 2 if one transmitter is failure and or all two transmitters? also in 2 of 3, what happen if one, two or all transmitters fail? I observed some process measurements employing these like in steam drum level measurement there were three level transmitters..

Thank you

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru
United Kingdom - Member - Indeterminate Engineering Fields - Control Engineering - New Member

Join Date: Jan 2007
Location: In the bothy, 7 chains down the line from Dodman's Lane level crossing, in the nation formerly known as Great Britain. Kettle's on.
Posts: 32212
Good Answers: 839
#1

Re: Process Measurement by 1 Out of 2 and 2 Out of 3 Logic

02/02/2011 2:04 PM

Transmitter failure is less likely than a loose wire on its output terminals these days.

1 out of 2 could be called "redundant backup". If one fails, the second comes on line to keep things moving.

2 out of 3 could be called "majority vote". If on fails, the other two ccarry on. If two fail, thhe thing stops.

Steam drum level failure is caught last-chance with the fusible plug - if the plug melts due to low water level, the contents of the drum empty into the firebox with spectacular results, though not quite as spectacular as catastrophic firebox crown failure while under pressure.

__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Reply
Reply to Forum Thread

Previous in Forum: Training   Next in Forum: Fire & Safety

Advertisement