Fault Level Evaluation of 11kV Network

02/20/2011 11:01 PM

Hello..

Can anyone please guide me on how to calculate the three phase fault level at each bus, while still maintaining power flow to substations A and B without overloading the feeders? For example, case 1: X0, Y0 are open, all other circuit breakers are closed.

Thank you very much!!

Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.

Good Answers:

These comments received enough positive votes to make them "good answers".
Guru
United Kingdom - Member - New Member

Join Date: Aug 2010
Location: Resting under the Major Oak
Posts: 4347
Good Answers: 181
#1

Re: Fault Level Evaluation of 11kV Network

02/20/2011 11:30 PM

Homework?

__________________
The reports of my death are greatly exaggerated.
Register to Reply
Participant

Join Date: Nov 2010
Posts: 4
#2
In reply to #1

Re: Fault Level Evaluation of 11kV Network

02/21/2011 12:53 AM

Yaya...:)

Register to Reply
Participant

Join Date: Mar 2011
Posts: 4
#14
In reply to #2

Re: Fault Level Evaluation of 11kV Network

03/08/2011 8:19 PM

Shenji, can u share me the coding?~

Register to Reply
Power-User
Engineering Fields - Electrical Engineering - New Member Engineering Fields - Mechanical Engineering - New Member

Join Date: Jan 2011
Location: Jakarta
Posts: 162
#3

Re: Fault Level Evaluation of 11kV Network

02/21/2011 1:06 AM

:-P

__________________
One system
Register to Reply
2
Guru

Join Date: Oct 2009
Posts: 2061
Good Answers: 169
#4

Re: Fault Level Evaluation of 11kV Network

02/21/2011 9:17 AM

Can you afford my consultancy fees?

Register to Reply Good Answer (Score 2)
Anonymous Poster
#5

Re: Fault Level Evaluation of 11kV Network

02/22/2011 1:08 AM

if u provide ur email id i can forward the copy of calculation in excel sheet for ur reference.

Register to Reply
Member

Join Date: Feb 2011
Posts: 5
#6
In reply to #5

Re: Fault Level Evaluation of 11kV Network

02/22/2011 1:34 AM

can you please also forward to this mail id Thank You,

CR4 Admin - email address removed

From the Site FAQ: Do not post phone numbers or email addresses. The CR4 Admin will delete all phone numbers posted in threads or comments, and we strongly urge you not to put up email addresses. You can share this information via the CR4 internal messaging system.

Register to Reply
Participant

Join Date: Nov 2010
Posts: 4
#7
In reply to #5

Re: Fault Level Evaluation of 11kV Network

02/22/2011 7:44 AM

thank u very much!!

CR4 Admin - email address removed

From the Site FAQ: Do not post phone numbers or email addresses. The CR4 Admin will delete all phone numbers posted in threads or comments, and we strongly urge you not to put up email addresses. You can share this information via the CR4 internal messaging system.

Register to Reply
Participant

Join Date: Mar 2011
Posts: 4
#11
In reply to #7

Re: Fault Level Evaluation of 11kV Network

03/06/2011 12:47 AM

can u email 2 me too?

Register to Reply
Participant

Join Date: Mar 2011
Posts: 4
#12
In reply to #5

Re: Fault Level Evaluation of 11kV Network

03/06/2011 12:49 AM

can u email 2 me too?

Register to Reply
Participant

Join Date: Mar 2011
Posts: 2
#8

Re: Fault Level Evaluation of 11kV Network

03/03/2011 12:26 AM

Hi Shengiboy, Have you successfully answered this question?

Register to Reply
Participant

Join Date: Nov 2010
Posts: 4
#9
In reply to #8

Re: Fault Level Evaluation of 11kV Network

03/03/2011 10:31 PM

hello there!

in the process of answering..

Register to Reply
Participant

Join Date: Mar 2011
Posts: 2
#10
In reply to #9

Re: Fault Level Evaluation of 11kV Network

03/04/2011 6:06 AM

okay, tell me when you are done. am also trying to solve it.

Register to Reply
Participant

Join Date: Mar 2011
Posts: 1
#13

Re: Fault Level Evaluation of 11kV Network

03/08/2011 11:27 AM

hey shengjiboy.do you have complete the calculation?

Register to Reply
Participant

Join Date: Mar 2011
Posts: 4
#15

Re: Fault Level Evaluation of 11kV Network

03/10/2011 12:16 AM

someone plz help me...share me the coding~

Register to Reply
Participant

Join Date: Mar 2011
Posts: 1
#16

Re: Fault Level Evaluation of 11kV Network

03/14/2011 11:59 AM

i know to do this 1..any payment?

Register to Reply Off Topic (Score 5)
Participant

Join Date: Oct 2010
Posts: 2
#17

Re: Fault Level Evaluation of 11kV Network

04/07/2011 4:09 AM

Assumptions: CB X0, Y0 are open and all other CBs are closed.

Impedance offered to 132X bus by system = Base MVA/Fault level

= 100/2700 = 0.037pu

Impedance offered to 132Y bus by system =0.056pu

impedance of T1 to base value = Tx. impedance*base MVA/Tx. MVA

= 0.267pu

impedance of T2 to base value =0.267pu

impedance of T3 to base value= 0.222pu

impedance of T4 to base value =0.222pu

impedance of line XA1 to base value = imp. in ohms *Base MVA/line KV^2

= 1.134pu

impedance of line XA2 to base value =1.134pu

impedance of line YB1 to base value =0.235pu

impedance of line YB2 to base value =0.235pu

impedance of line AB4 to base value =0.471pu

On the occurance of a fault on bus 11B1 - 11B2, the effective impedance =0.23pu (draw the single line diagram and estimate the equivalent impedance)

Fault level on 11B1 / 11B2 = base MVA/effective impedance upto the bus

= 434.53MVA, 22807 Amps.

On the occurance of a fault on bus 11A1 - 11A2, the effective impedance =0.373 pu (draw the single line diagram and estimate the equivalent impedance)

Fault level on 11A1 / 11A2 = base MVA/effective impedance upto the bus

= 268.13 MVA, 14073 Amps.

Effective impedance on 11X1 = 0.258pu (this needs delta to star conversion and series parallel combination of impedance, in the single line diagram)

Fault level on 11X1 = 387.44MVA, 20335 Amps.

Same fault level on 11X2.

Effective impedance on 11Y1 = 0.205pu (this needs delta to star conversion and series parallel combination of impedance, in the single line diagram)

Fault level on 11Y1 = 488.48MVA, 25638 Amps.

Same fault level on 11Y2.

I checked these values with ETAP demo vesion and obtained more close results.

Register to Reply Score 1 for Off Topic
Register to Reply 17 comments

Good Answers:

These comments received enough positive votes to make them "good answers".
Copy to Clipboard

Users who posted comments:

Abdul_Gafoor_MK (1); Anonymous Poster (1); electricalexpert65 (1); gemstar (1); jaiZi (1); loadshare (1); mprajaneb (1); shengjiboy (3); Taj gouda (2); theravellerzt (4); TonyS (1)

Previous in Forum: ACDB/ DCDB   Next in Forum: NGR to be Put on Transformer

Advertisement