Charge all batteries to same level, or up to maximum possible level, and after that join them in series and connect output (12x32v= 384V) to A Load of 1 Amp (384 watt) and check the voltages on each battery, at start, after an hour and after 2 Hours, faulty batteries will show lower voltages and good one will stay up even after two hour,
Ah, so now it's a possible one dud battery in a bank of 32? OK.
Monitor the performance of the battery bank over time.
Carry out equipment-exchange planned maintenance on the batteries using a range of good spares.
Individually test each removed battery for performance against a set of criteria, and pass/fail the battery against that test result.
Renew failed batteries.
Place passed batteries and new batteries into the equipment-exchange spares stock.