I am currently working in the construction of a 33KV/11KV substation.
I do not have cable schedule.
How can I create a cable schedule? Through studying the connections inside the Relay and control panel, 33KV Vaccuum circuit breaker etc.
The substation has following equipment:
Current transformer with ratio
100-200/1A
with three nos of cores one for metering rest for protection
1. Step down transformer 33kv/11kv without OLTC , an oil temperature and winding temperature indicator ,Dyn11, oil natural air natural , buccholz relay
2. Vacuum circuit breaker crompton greaves
3. relay and control panel having an over current relay , a master trip relay and two number of auxilliary relay (I think the two number of auxiliary relays are for oil temperature indicator and winding temperature buccholz relay )
4. Incomer + 4nos of feeders
with energy meter fitted in them all respectively and also
each having a over current relay and
breaker tripping control
Do these have their own separate current and voltage transformers inside them
"Almost" Good Answers: