I would like to discuss about the storage of Power Transformer. We are having 313 MVA and 195 MVA Power Transformer at our power generation site. Plant was running till 2012. But since last one year plant is in shut down condition and it will be in this condition for next 1 or 2 year. Currently transformer is in charged conditions. But, now Top managers are insisting to make it off to cut the no load losses. So what should do in this condition to maintain the transformer in good condition. Is it advisable to make it off for longer period ? We asked OEM, but they are saying to store the transformer with maintaining the all parameters as it is in charged condition
.
please give suggestion or share your experience in the matter.