Hi,
I have 6(six)- 2 per phase 25 kv 500 mcm XLPE cu power cable which will be routed from 25 kv bus to switchgear building through road crossing heavy duty concrete trench(grade raceway) approximately 55m distance. How I could put my cable? If I put flat formation with 2 layer then what would be the spacing between layers. cable dia 45 mm and what woud be spacing between two cables. Could I put A-B-C from left and on top layer same sequence A-B-C from left. Should I have to calculate any de-rating of ampacity since trench would be be covered.Please advise.