whether routine tests while manufacturing or testing while commisioning of the cables
if it is tests for manufacturing
for each stage hv test and insulation test will be done
while in commisioning of the cable we will check the ir values and hv test for the insulation . in critical areas we will go for the current carraying capacity test by flowing high current through the cable
also we will find the resistance of the cable by volage drop test.
What are 1.Sheath Integrity Test 2.tan delta 3. Hot Deformation 4. HI POT Test 5.Capacitance Test 4.Inductance test & What are the procedures for conducting the tests?
__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Consult locally a qualified Electrician instead. After all, the <...Cable...> cannot be seen from here, and neither can the end Client's requirements, which will drive the <...procedures...>.
__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
"Almost" Good Answers: