Hello thinkers, I have a question for you! How do I retrofit a 2000 amp service without losing power to the 250 units it serves. I need to limit my down time to less than 24 hour periods. The current service is 35 years old and showing signs of wear and maintenance problems for the maintenance staff. It is a 1600 amp bus duct with 29 switches to disconnect feeders going up the riser area. Each feeder takes care of about 8 units.

I will reward the right answer with the design contract or a fee for their help if I get the job.

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru
Canada - Member - If there is a way to screw someting up, there is someone to do so! Safety - Hazmat - New Member

Join Date: Mar 2007
Location: Iqaluit, NU. Canada
Posts: 1854
Good Answers: 140
#1

Re: 2000 amp Service, 3 phase 4 wire in HI RISE Building.

03/23/2009 8:03 AM

What is getting replaced? The main switchgear? The bus feeding the floors? The individual taps off of that duct? What is the incoming system voltage?

__________________
Joe Contractor to Electrical Inspector, "What do you mean you are going to make me follow the code?".
Reply
Reply to Forum Thread

Previous in Forum: Merlin Gerlin 250 amp mccb   Next in Forum: Nikola Tesla and the Whitefire Experiments

Advertisement