Given below is a typical problem that we faced in our CPP for which we don't have a satisfactory answer. (WARNING - A long text follows!!!!)
The electrical system layout is briefed below:
There are 8 DG sets each of 11kV, 8145kVA, 0.8pf, 50Hz and 750RPM. These generators are connected to single 11kV bus-bar with no bus-coupler. The power is evacuated to the distribution substation through 2 cable feeders namely AC8 (4 runs of 11kV XLPE cables per phase) and AC3 (2 runs of 11kV XLPE cables per phase). The AC8 feeder feeds the 11kV NGEF bus and AC3 is connected to 11kV Voltas bus in the substation. The tie breaker in between NGEF and Voltas bus is kept open during normal running conditions since the AC3 feeder does not have sufficient capacity to share the plant load with AC8 when the tie CB is closed. In addition to the DG sets, we have facility to draw power from the grid through two 110/11kV, 40MVA transformers namely TR1A and TR1B connected to Voltas and NGEF bus respectively. We do not run in parallel with the grid since our in-plant generation is sufficient to meet the power demands of the complex. We take the grid support only during plant contingencies and while starting large capacity HT motors.
Since all the HT motors are connected to the NGEF Bus, while starting these HT motors, we synchronize with the grid through TR1B (Loop - CPP 11kV bus - AC8 - NGEF Bus - TR1B, CPP 11kV bus - AC3 - Voltas bus, tie CB between NGEF and Voltas bus open). However, during one such occasion, TR1B was not available and we had to synchronize with the gird through TR1A (Loop - CPP 11kV bus - AC3 - Voltas bus - TR1A - Tie CB - NGEF bus - AC8 - CPP 11kV bus). We had to close the tie CB since the motor was connected to NGEF bus. Motor details - 11kV, 3.5MW, 1485 rpm, 0.9pf, Ist/In - 3.0. The IM drives a centrifugal compressor.
After synchronization of CPP with the grid through TR1A, clearance for motor starting was given. When the motor started, both AC8/AC3 feeder upstream and downstream CB tripped on earth fault and the entire plant load fell on the grid and CPP went for a black out. The base load at the time of starting of the motor was 25MW at 11kV, 50Hz. The motor survived the starting.
Till now, except in the above case, the starting of these motors have never caused the E/F to pick up. Also, when the motors are started with the configs. 1) CPP 11kV bus - AC8 - NGEF - TR1B, CPP 11kV bus - AC3 - Voltas with tie CB open. 2) CPP 11KV bus - AC8 - NGEF - Tie CB - Voltas - TR1A with AC3 feeder switched OFF have never caused the E/F relays to pick up.
What could be the reason for this behavior of the system?
"Almost" Good Answers: