Pre-Commissioning and Commissioning

07/01/2010 3:31 AM

Hello sir's.

whats the difference between pre-commissioning and commissiong, and whats the job responsibilities and activities involved.

thanks

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Anonymous Poster
#1

Re: pre- commissioning and commissioning

07/01/2010 4:11 AM

pre- commissioning :- all the testing and checks which shall be done before the operation or recieve power to the equipment like cable continuity test , insulation resistance test, hi-pot test ,leak test ,instrument calibration , primary injection of CT,protection relay check ,.....

commissioning :- all the activities and testing which shall be done during start-up of the machine or the equipment including the maneuver and energize (power recieve to the equipment) like interlock test, Electric parameter mesuring , vibration check , nose measure,synchronization,flow check....

Reply
Power-User

Join Date: Jun 2010
Posts: 348
Good Answers: 10
#2

Re: pre- commissioning and commissioning

07/01/2010 5:41 AM

Terminology is synonimous to; cold commissioning and hot commissioning.

__________________
Knowledge sharing is a WIN-WIN situation
Reply
Power-User
United Kingdom - Member - Not quite retired Member

Join Date: Aug 2012
Location: Up an araucaria araucana tree, South London, United Kingdom
Posts: 132
Good Answers: 7
#5
In reply to #2

Re: pre- commissioning and commissioning

08/03/2012 10:21 AM

I would be glad of references for this proposition and about hot and cold comissioning generally.

Reply
Active Contributor

Join Date: May 2010
Posts: 10
#3

Re: pre- commissioning and commissioning

07/01/2010 5:47 AM

Before commissioning and during commissioning.

Some activities need to be carried out before commissioning for example complete equipment testing viz. HV, Primary injection. secondary injection etc will be carried out in pre-commissioning stage. Important tests like trip test, mechanical operation etc will be repeated during commissioning stage.

Reply
Guru

Join Date: Oct 2009
Posts: 2061
Good Answers: 169
#4

Re: pre- commissioning and commissioning

07/01/2010 7:39 AM

"COMMISSIONING" is putting into service.

And, pre-commissioning is - making the system and/or equipments ready for putting into service.

Reply
Guru
Engineering Fields - Mechanical Engineering - New Member

Join Date: May 2008
Location: CHENNAI, TAMIL NADU, INDIA.
Posts: 1851
Good Answers: 65
#6

Re: Pre-Commissioning and Commissioning

04/05/2013 12:37 PM

Dear friend,

PRE-COMMISSIONING refers to the individual equipment trial/testing while there can be several equipments, each with different in-put-output parametres and make ready for commercial production, and make a smooth starting of commercial production and reach the rated capacity.

If this exercise is not conducted, then during commercial production i.e commissioning, the plant has to be stopped - for example, leakages, electrical fault, vaccuum problem etc.

COMMISSIONING refers to OVER-ALL/COMBINED TRIAL and then start Production with raw materials input, and get the end product.

POST-COMMISSIONING - will refer to activities/rectifications to be carried out by taking a planned shut-down of the plant,for different type of problems, in different equipments and fine tune the equipments, and re-start the plant to achieve the targets.

DHAYANANDHAN.S

Reply
Reply to Forum Thread 6 comments
Copy to Clipboard

Users who posted comments:

Anonymous Poster (1); dhayanandhan (1); electricalexpert65 (1); Geoffrey36 (1); kanmano (1); mountk2 (1)

Previous in Forum: Does slower fan consume less energy?   Next in Forum: Neutral Grounding Resistor

Advertisement