Dear All,
It is reported that the 300 MW Steam Turbine supplied and installed by DongFang Electric Corporation (DEC) at Durgapur Projects Limited (DPL) has been out of service for the last 3 months. Can anybody highlight on the nature & extent of the problem, i.e., design issues, manufacturing related, Wrong O & M Practice or something not taken care of during erection and commissioning cycle?