Is it necessary to have top sheet erection completed for commencing the flooring works in a factory building. We are planning to go for VDF (vacuum dewatered flooring)

Regards,

Prashanth

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru
United States - Member - Member Engineering Fields - Electrical Engineering - Electrical Construction

Join Date: Apr 2010
Location: Mid Western USA - The Corn Belt
Posts: 1439
Good Answers: 58
#1

Re: Factory Sheeting vis-a-vis Flooring

09/16/2010 3:11 PM

If "top sheet erection" implies the roof of the structure then I would say yes unless you are in an area that will not get rain, high humidity, or heavy dew.

The VDF still needs curing time after dewatering and re-introduction of water/moisture prior to cure is a no-no with this type of floor.

Use Google and "vacuum de-watered flooring" for more information.

Good Luck!

__________________
The first 5 days after a weekend are always the hardest................................
Reply
Reply to Forum Thread

Previous in Forum: Precast Plinth Beams   Next in Forum: Steel Bollards
You might be interested in: Flooring Materials, Fiber Optic Probes

Advertisement