Anonymous Poster

Generator

09/16/2010 11:56 AM

what are the tests are carried in generator

Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Guru
United States - Member - Member Engineering Fields - Electrical Engineering - Electrical Construction

Join Date: Apr 2010
Location: Mid Western USA - The Corn Belt
Posts: 1439
Good Answers: 58
#1

Re: Generator

09/16/2010 12:31 PM

Based on the limited content of your request, I will assume post manufacture, pre start-up.

Post Installation – Pre Start-up:

1. Verify that Genset has been physically installed per the manufacturers' specification i.e. concrete pad, proper environment (indoor or outdoor), hold down devices in place and secure, shrouds and guards in place.

2. Verify all shipping material removed (plastic, cardboard, muffler shipping plug, manuals, ect).

3. Correct lubricant and proper level in crankcase and drain plug secure.

4. Correct coolant/antifreeze and proper level and drain plug secure.

5. Air filter element installed and secure.

6. Verify fuel connection(s) and availability.

7. Correct connections and phasing of line conductors from Genset to transfer switch/load.

8. Megger check conductors indicated in Item 7. (above)

9. Battery connected and charged.

10. Battery charger and block heater (if required) are connected to power source.

11. Disable transfer switch.

12. Attach load bank set cables to generator line lugs in transfer switch.

13. Start Genset.

14. Check for fuel/coolant/oil leaks.

15. Engage master on load bank set and ramp up to load as prescribed by the manufacturer.

16. Maintain load on generator for time period as prescribed by the manufacturer.

17. After conditions of Items 15 and 16 (above) are met, disengage master on load bank set.

18. Allow Genset to run un-loaded for extract cool down as prescribed by the manufacturer.

19. After conditions of Item 18 (above) are met, shut down Genset.

20. Check for fuel/coolant/oil leaks.

21. If all items above are successful, complete manufacturer pre/post start up documents.

This list is "general". Requirements will vary (sometimes greatly) between manufacturers and Genset types.

__________________
The first 5 days after a weekend are always the hardest................................
Reply Score 1 for Good Answer
Guru
United Kingdom - Member - Indeterminate Engineering Fields - Control Engineering - New Member

Join Date: Jan 2007
Location: In the bothy, 7 chains down the line from Dodman's Lane level crossing, in the nation formerly known as Great Britain. Kettle's on.
Posts: 32175
Good Answers: 839
#2

Re: Generator

09/17/2010 3:21 AM

The ones that are stated in the manufacturer's instruction manual.

__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Reply
Guru

Join Date: Oct 2009
Posts: 2061
Good Answers: 169
#3

Re: Generator

09/17/2010 4:34 AM

Are you a generator manufacturer or a user?

Reply
Reply to Forum Thread 3 comments

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Copy to Clipboard

Users who posted comments:

electricalexpert65 (1); KJK/USA (1); PWSlack (1)

Previous in Forum: Contactor Between VFD and AC 3 Phase Induction Motor   Next in Forum: Step By Step Procedure For Primary And Secondary Injection Testing

Advertisement