I'm about to get started on my new house and I have a question for you gurus. I had a soil test done by a geotechnical engineer and his report states that the expansive clay soils on my building site are not suitable for constructing the house upon, as is. He recommends 2 methods of construction to deal with the soil. The first method is that if I want to construct a slab-on-grade, then I need to undercut the entire building site by 4 feet and replace the clay soils with good compacted fill. The second is if I want to build on a crawlspace or raised slab foundation, then I can dig the footing trenches to a depth of 4', backfill them with 2 feet of compacted crushed stone, pour concrete footings on top of the stone, and then use concrete block to raise the foundation to desired floor heights, ensuring that I have a least 2 feet of good compacted fill under the slab. The 2nd option fits more into what we are wanting to do since we want a raised slab. That said, my lot has approximately 2 feet of slope from one side of the house to the other. The foundation contractor has proposed digging the trenches with the slope. Meaning he'd dig the North end 4 feet and the South end 4 feet deep, backfill with the stone, and pour concrete footings on top following the grade. That would still leave the South end 2 feet lower than the North end. The slab would then be leveled by placing more block on the south end to bring it up level. I have some reservations about doing it this way. I would think that the house would tend to want to slide downhill to the South end. I guess it's really no different than having a stepped footing though, perhaps better since the footings would be continuous. But still I have reservations and think it would be better to either cut the slope out or bring the low end up level with the high end with compacted fill and then dig the footings 4 feet deep through the level grade. The thing is that building the low end up would add about $3000 to the foundation costs and the foundation contractor assures me it's unnecessary. He also makes a good point that doing that would mean the footing is shallower, as compared to the surrounding grades, and in the newly compacted fill verses deep in the existing soil. The downside to cutting the slope off and leveling the grade is that I'd need a good many extra block to then bring the floor level back up to desired height as well as need additional fill hauled in to fill the void between the footing walls. Another option I thought about is to dig the footings on the North end 6' deep so that the bottom of them is then level with the bottom of the footings on the South end, and just leave the existing clay on the North end. I'd still have plenty of compacted fill above the clay by the time I get back up to the desired floor height and I wouldn't need the extra fill, just the block. But doing it that way means I'd need wider trenches so that the block mason can get down there to lay the block. Seems nothing is without problems and extra expense, so I'm torn as to what to do.
I intend on talking with the engineer about this, but it seems what the foundation contractor purposes is the common excepted practice in the area. I took a drive through a new development today and found several houses that are being done this way, some on conventional foundations and some on raised slabs. So I'm pretty sure the engineer is going to say it's ok, but at the same time he accepts no responsibility if I have problems in the future. Anyway, just wanted to get your input on this. Thanks
PS. I'm in North Mississippi, if that matters.