Hi friends
Can you pl suggest me.
In machining section say for example in turning center
How to calculate the OEE/shift if the set up change is more than one and cycle time or no of piece/minute is different.
For example..
In shift A.
Part No A cycle time is 75seconds
Part No B cycle time is 70 Seconds
Part No C cycle time is 95second
Part No D cycle time is 100seconds.
Shift length is 8 hours.
Planned break hours:60min
Down time;80min(Including 4 setup change)
Part No A produced:50 pieces
Part No B produeced:75pieces
Part No C produced:56 pieces
Part No D produed:54 pieces.
In Above example can you pl calculate the OEE.
If you give the brief explanation with example which will be helpful for me.