Is a separate PQR required to weld when PWHT is required on the steel when fabricating a vessel to Sec VIII?

Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru

Join Date: Jan 2010
Location: Mineral wells Tx
Posts: 630
Good Answers: 34
#1

Re: Special WPS/PQR For Welds That Require Post Weld Heat Treatment

05/11/2012 2:23 AM

To determine this question, you sould add to what welding process we are talking about. WPS/PQR are referenced in ASME IX. Then:1.- Check what welding process you will use. (QW252 to QW265).2.-For your welding process wich are the "Essential Variables" (Any change in a essential variable, requiere a new WPS/PQR).

PWHT (QW 408) is essential variable for most of the welding process. The final answer is: YES, you need a separate WPS/PQR.

Regards. WP