Dear Members
I have to do hydrotest as per UG-99B (1.3*MAWP).
But as per one of the project specification, hydrotest shall be performed as per the code, however MAP shall be used in lieu of MAWP.
What is the significance of this?
Also if i am having a higher thickness margin (given thk. - required thk.), the MAP will be higher. Also the hydrotest pressure.
The vessel is failing to hydritest pressure due to this. If increased the vessel thickness, the MAP will also increase again.
Kindly advise
Regards,
vGsh