How to Estimate Cable Tray Weight Onboard?

11/29/2012 4:36 AM

How to estimate the weight of cable tray onboard an offshore drilling unit, does it have a defined relations with the cable size and number?

Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.
Guru
Engineering Fields - Power Engineering - New Member

Join Date: May 2007
Location: NYC metropolitan area.
Posts: 3230
Good Answers: 444
#1

Re: How to Estimate Cable Tray Weight Onboard?

11/29/2012 11:49 AM

1. Get the cable schedule,

2. Get manufacturers' catalogs and look up the weight per foot,

3. Multiply and add appropriately to get overall weight per foot,

4. Don't forget the weight of the tray and its mounting accessories,

5. Multiply by the total length of the run.

__________________
“Tell me and I forget. Teach me and I remember. Involve me and I learn.” Ben Franklin.
Register to Reply
Active Contributor

Join Date: Aug 2012
Posts: 22
#3
In reply to #1

Re: How to Estimate Cable Tray Weight Onboard?

11/29/2012 7:49 PM

Hi, thanks for you help. But what about during the basic design, while we dont have required materials available, and most of importance, we dont have time in contract. Just a rough estimation is OK. Let's say, the cables are 500 tons, then the cable tray and accessories will be a percentage*500 tons, eg 10%*500=50 tons. Do we have that rough percentage?

Register to Reply
Guru
United Kingdom - Member - Indeterminate Engineering Fields - Control Engineering - New Member

Join Date: Jan 2007
Location: In the bothy, 7 chains down the line from Dodman's Lane level crossing, in the nation formerly known as Great Britain. Kettle's on.
Posts: 32175
Good Answers: 839
#4
In reply to #3

Re: How to Estimate Cable Tray Weight Onboard?

12/05/2012 6:10 AM

"Undefined we" alarm.

"We" don't otherwise "we" wouldn't be asking.

__________________
"Did you get my e-mail?" - "The biggest problem in communication is the illusion that it has taken place" - George Bernard Shaw, 1856
Register to Reply
Guru
United Kingdom - Member - New Member

Join Date: Aug 2010
Location: Resting under the Major Oak
Posts: 4347
Good Answers: 181
#2

Re: How to Estimate Cable Tray Weight Onboard?

11/29/2012 2:30 PM

Failing that guess

__________________
The reports of my death are greatly exaggerated.
Register to Reply
Register to Reply 4 comments
Copy to Clipboard

Users who posted comments:

lovekobelxm (1); PWSlack (1); RAMConsult (1); TonyS (1)

Previous in Forum: Can We Use Class-X CT in Place of 5P10?   Next in Forum: Implementing a Control System

Advertisement