To preface my question, let me give some background information.
On a solar energy project, we have an ABC CCW rotation coming from the utility. The inverter manufacturer wants an ABC CW rotation. We are currently set up with the proper phasing, according to the utility. There are 5 medium voltage transformers (34.5kVac-330Vac) paralleled together in a circuit. A is A, B is B and C is C, throughout. The inverter manufacturer is wanting us to swap A and C phases, in the middle of the circuit, to give the inverter skid a CW rotation. We have been producing nominal power for a few weeks as we are. My question is what would happen if we swapped A and C phases, in the middle of the circuit, to make the inverter manufacturer happy.
Our substation is 34.5kVac-230kVac. We are definitely ABC CCW from the utility.
This is my 1st solar project. I've never seen a power plant be able to sync to the grid with no sync circuits.
"Almost" Good Answers: