Previous in Forum: Making Endless Woven Glass Fabrics   Next in Forum: Paint on Silicon Sealant
Close
Close
Close
23 comments
Rate Comments: Nested
Participant

Join Date: Oct 2014
Posts: 3

Nitrogen Purging to Prevent Internal Oxidation

10/25/2014 8:04 AM

Our firm is obligated to purge a gas pipeline of a maximum diameter of 24" from air utilising nitrogen gas. This is to prevent additional internal oxidation of the steel pipeline. A pressure of 10 psi has been specified in the contract but no additional specification has been requested. The volume of the network is 2800 m3 and the purging is required as the last step prior to commissioning.

Considering that nitrogen purging is normally adopted when flammability is an issue, I found very little information regarding the specification of the required procedure for the purpose of preventing internal oxidation. As the junior engineer I am in charge of associated research in this matter. provided this brief background, I require assistance in regards with following issues:

1) what is the maximum acceptable level of oxygen to ensure the prevention of internal oxidation? i.e.: what is the required concentration of nitrogen in the network ?

2) Is there any general code of design and practice dealing with this issue specifically? ( Again, I have found a substantial chunk of codes concentrating on the flammability of the gaseous mixture, but almost none giving guidelines regarding the internal corrosion ensued from the presence of oxygen and associated nitrogen purging to prevent the matter)

3) What will be considered a feasible method for the purging itself? The option of cyclic purging is rather expensive considering the amount of nitrogen required. Since this is a one-off task, purchase of nitrogen generator is out of question for the company, additionally there is no contractor available in the area offering such services. So far, the proposed method to conduct the task is utilisation of a vacuum pump to eliminate the internal air, and subsequent injection of nitrogen to the network.

Your input is very much appreciated.

Regards

Register to Reply
Interested in this topic? By joining CR4 you can "subscribe" to
this discussion and receive notification when new comments are added.

Good Answers:

These comments received enough positive votes to make them "good answers".

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Guru

Join Date: Feb 2011
Posts: 7025
Good Answers: 207
#1

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 8:33 AM

your firm needs to hire a qualified Jr engineer

Register to Reply
Guru
Popular Science - Weaponology - New Member Fans of Old Computers - PDP 11 - New Member Technical Fields - Architecture - New Member Hobbies - HAM Radio - New Member

Join Date: Oct 2009
Location: Maine, USA
Posts: 2168
Good Answers: 71
#2

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 8:55 AM

"but no additional specification has been requested"...and that's where the problem is. Before accepting a contract, all of these questions you have should be specified!

__________________
Tom - "Hoping my ship will come in before the dock rots!"
Register to Reply
Guru

Join Date: Oct 2008
Posts: 42355
Good Answers: 1693
#3

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 10:04 AM

1) What is the level specified in the contract?

2) What is the code, or requirement specified in the contract?

3) The method specified in the contract, or by the code or requirement specified in the contract.

As stated, If your company has no one on staff who even knows where to look for these answers, they should retain a competent pipeline consulting company or quit the job entirely.

Google "pipeline construction".

Pipeline Safety - eCFR - Code of Federal Regulations

Register to Reply
2
Guru
Engineering Fields - Electrical Engineering - Been there, done that. Engineering Fields - Control Engineering - New Member

Join Date: Dec 2008
Location: Long Island NY
Posts: 15600
Good Answers: 981
#4

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 10:23 AM

You should simultaneously propose a method for approval and insist on an approved method to complete this contract. In other words an e-mail or memo saying, this is how you will do this unless the customer specifies a different technique.

If I were to do this, I would vacuum pump down the pipe to an approved vacuum of maybe 100 torr to remove an acceptable amount of oxygen from the pipe. Then fill the pipe with bottled nitrogen to the approved pressure.

I would not attempt any method until an approved method had been agreed upon, in writing. (A simple e-mail agreement would do for me.)

__________________
"Don't disturb my circles." translation of Archimedes last words
Register to Reply Good Answer (Score 2)
Guru

Join Date: Oct 2008
Posts: 42355
Good Answers: 1693
#5
In reply to #4

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 10:25 AM

OP could just fill the pipeline with water.

Register to Reply
Guru

Join Date: Feb 2011
Posts: 7025
Good Answers: 207
#6
In reply to #4

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 11:47 AM

I'm not in agreement with you on this one. I think he does need better communication and clarification of his contractual obligation but I think the vacuuming is unnecessary and costly. if the contract calls for purging and sealing why not meet those specs?

Register to Reply
Guru
Engineering Fields - Electrical Engineering - Been there, done that. Engineering Fields - Control Engineering - New Member

Join Date: Dec 2008
Location: Long Island NY
Posts: 15600
Good Answers: 981
#9
In reply to #6

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 12:14 PM

I'm just using my background and experience with recommending a vacuum pump down purge. Pumping down to 1/Y of an atmosphere of pressure provides a metric for completing a process while confirming a reasonably sealed system. The problem, as I see it, is the lack of specificity in how one properly purges this line and demonstrating that a purge was performed properly. Just measuring the amount of gas pushed into a container tells me nothing unless I know the path this flow takes.

__________________
"Don't disturb my circles." translation of Archimedes last words
Register to Reply
Guru

Join Date: Feb 2011
Posts: 7025
Good Answers: 207
#10
In reply to #9

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 1:33 PM

it should have been clearly laid out in the contract language......they have a deficiency there. I understand it as, "install a pipe, seal it, purge with nitrogen. seal again with 10 psi nitrogen." deliver to customer, contract Complete.

Register to Reply
Guru

Join Date: May 2009
Location: Wolfe Island, ON
Posts: 1357
Good Answers: 109
#8

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 12:00 PM

Not familiar enough with pipe lines but nitrogen purging is used in both the water well and oil well industries. Maybe this will help.

https://www.rigzone.com/training/insight.asp?insight_id=329&c_id=4

http://www.epa.gov/region1/lab/qa/pdfs/EQASOP-GW001.pdf

__________________
If they want holy water, tell them to boil the hell out of it.
Register to Reply
Guru
Hobbies - DIY Welding - New Member

Join Date: Sep 2007
Posts: 1601
Good Answers: 58
#11

Re: Nitrogen Purging to prevent internal oxidation

10/25/2014 11:35 PM

Nitrogen purging is not required. Your steel pipeline can be kept free of oxidation by maintaining the relative humidity below 50%.

Register to Reply
Participant

Join Date: Oct 2014
Posts: 3
#13
In reply to #11

Re: Nitrogen Purging to prevent internal oxidation

10/26/2014 2:56 AM

the thing is there has been some development of mild internal oxidation which has resulted in the client requesting nitrogen purging. This is to stop further oxidation within the line.

Register to Reply
Participant

Join Date: Oct 2014
Posts: 3
#12

Re: Nitrogen Purging to prevent internal oxidation

10/26/2014 2:51 AM

A big Thanks to those of you replying without a lousy side of sarcasm. Lack of clarity in the contract is a valid issue here. Nitrogen purging has been mentioned only once in the contract in fine fonts and as a foot note to one of the clauses regarding the quality of pipeline. The principal issue wiv contacting the client for instruction is their lack of sufficient in-house knowledge regarding the matter. Additionally, internal rusting of the steel is rarely ever an issue in the area (meaning that the client itself is not aware of the technicality of nitrogen purging as a mean to stop oxidation.) Therefore, requesting for instruction would result in them asking for 100% concentration of nitrogen within the network without any knowledge behind it. Thereby we are trying to gather a feasible method based on (any) codes of practice or standards since none has been specified in the contract. The biggest difficulty for any negotiation here is the fact that this is a traditional type of procurement. So the proposed design has been paid for long before we accepted the contract.

Register to Reply
Guru

Join Date: Jul 2007
Location: Commissariat de Police, Nouvions, occupied France, 1942.
Posts: 2599
Good Answers: 77
#14
In reply to #12

Re: Nitrogen Purging to prevent internal oxidation

10/26/2014 3:29 AM

Then you should be asking your Contact Manager rather than some bunch of Muppets on the internet.

Nitrogen, actually, is the cheapest bulk gas available that hasn't got any water in it, and that is why it is used. Do check that the line has been tested hydraulically to a higher pressure before introducing gas under a lower pressure.

__________________
Good moaning!
Register to Reply Score 1 for Good Answer
Guru

Join Date: Oct 2008
Posts: 42355
Good Answers: 1693
#15
In reply to #12

Re: Nitrogen Purging to prevent internal oxidation

10/26/2014 4:03 AM

It seems that your client is not the only entity with a lack of sufficient in-house knowledge regarding the matter.

Register to Reply
Guru

Join Date: Feb 2013
Posts: 2004
Good Answers: 31
#16

Re: Nitrogen Purging to prevent internal oxidation

10/26/2014 5:43 AM

Your post makes no sense at all. A utility who owns and runs a 24 inch gas mains and stipulates a pressure of 10psi in a contract has issued you with standards and spec to test and commission this line.

There are many specs for purging pipelines as these pipelines are used world wide by many companies in the gas business. Nitrogen is a common gas to use to expel air from packaging and pipelines.

What is the Typical method of procurement you mention? If the design is paid for upfront, who is doing the design now? No design is built to the original design as mods and variations are an ongoing process.

Your project manager and contract manager would have this info as it is written in the original tender docs, along with the standards to use. Any gas mains owner will have the info and standards for his 24 inch gas mains on record.

It looks to me that you are in ZA and if I am correct, you have plenty standards for gas mains and purging and if you are in Europe you should not be working on gas mains as the requirements for this would ensure you know what you are doing.

The whole post is nonsensical.

Register to Reply
Power-User

Join Date: May 2007
Posts: 105
Good Answers: 3
#17

Re: Nitrogen Purging to prevent internal oxidation

10/26/2014 1:47 PM

It is a fact that Nitrogen is extensively used for preventing oxidation in Pressure Vessels in Chemical Plant projects until the plant is erected and commissioned, as it takes a long period of idle time before the vessels are erected & commissioned.

If the Client wants Nitrogen purging of the pipeline, I believe it has to be filled and maintained under some positive pressure above atm. (need not necessarily be as high as 10 psig which is almost 1.7 bar). If the gas pipeline has to be kept without internal corrosion, there is no other way than to fill the full vol. of pipe with Nitrogen under +ve pressure to account for some leakage. You can only claim extra costs on the basis of lack of clarity in the contract regarding your scope.

Register to Reply Score 1 for Good Answer
Guru

Join Date: Oct 2008
Posts: 42355
Good Answers: 1693
#18
In reply to #17

Re: Nitrogen Purging to prevent internal oxidation

10/26/2014 2:15 PM

No one knows what the client wants.

"Nitrogen purging has been mentioned only once in the contract in fine fonts and as a foot note to one of the clauses regarding the quality of pipeline" and no one has asked for clarification.

OP doesn't want the client to know that his company is"without knowledge" because he believes that, "requesting for instruction would result in them asking for 100% concentration of nitrogen within the network without any knowledge behind it."

The pipeline is already rusted, so purging will arrest further oxidation, but not insure the quality of the pipeline, which will be determined by the client.

Register to Reply
Guru

Join Date: Feb 2013
Posts: 2004
Good Answers: 31
#19
In reply to #17

Re: Nitrogen Purging to prevent internal oxidation

10/26/2014 5:55 PM

10 pound per square inch (psi) = 0.68 Bar.

Register to Reply
Power-User

Join Date: May 2007
Posts: 105
Good Answers: 3
#20
In reply to #19

Re: Nitrogen Purging to prevent internal oxidation

10/27/2014 4:37 AM

You are right. Actually, I meant 1.7 bara considering atm. pr. as 1 bara.

Thanks.

Register to Reply
Guru

Join Date: Feb 2013
Posts: 2004
Good Answers: 31
#21
In reply to #20

Re: Nitrogen Purging to prevent internal oxidation

10/27/2014 7:48 AM

Not a problem. BarA being absolute pressure and BarG being gauge pressure of course.

However, purging with nitrogen would not quite help at 10psi.

Register to Reply
Guru

Join Date: Jan 2010
Location: Mineral wells Tx
Posts: 630
Good Answers: 34
#22

Re: Nitrogen Purging to Prevent Internal Oxidation

10/28/2014 6:08 AM

HI ZA

Is similar to that used for long term storage

Preservation after pre-commissioning has to be discussed separately with the client.

The end of guarantee from vendors is to be considered since the requirements in this procedure relate to prolonged storage of material (expected duration of storage 1 year or more).

Specific preservation requirements of vendors will be followed as far as possible. If there is a conflict between manufacturer's recommendation and the recommendation in this procedure, the vendor's recommendation shall take precedence.

The extent of preservation will depend on the anticipated period that the equipment is to be preserved. This is to be handled in close conjunction with the client's representative and the vendor.

Rust preventatives and desiccants are sold under various brand names and have to be field purchased as required. Before purchasing starts, agreement has to be reached between field and client on brands and types of rust preventatives and desiccants.

  • 1.-Systems containing hydrocarbon will be sprayed, flushed or filled with a suitable oil or inert powders..

· 2.- Nitrogen blankets will be applied and maintained on stainless equipment.

Apply nitrogen blankets preferably after all internal work is finished in order to avoid extensive purging operations. Nitrogen in a vessel can be dangerous. Apply all necessary warning plates near all vessel entrances.

All construction personnel shall be familiarized with the risks of nitrogen blankets. This instruction is the personal responsibility of the safety engineer.

Austenitic stainless steel items can be internally protected in accordance with the following preservation method:

· Shop installed gaskets and blind flanges shall remain un removed until installation of piping.

· Maintenance of a nitrogen blanket on austenitic stainless steel is imperative.

· The nitrogen gas pressure in the equipment shall be checked regularly.

· If the pressure is below 0.5 bar(g), a refill with dry nitrogen is required. The oxygen content shall be less than 2 % by volume measured at the flushing outlet which shall be a maximum distance from the flushing inlet. The refill shall not start before nitrogen pressure is at 0.1 bar(g). When a pressure of less than 0.5 bar(g) is recorded, close monitoring is required (at least one a week).

· When depressurizing is required during erection of equipment, it is imperative that the nitrogen blanket immediately be restored when this action is completed. Equipment shall be absolutely dry before refill can start. Temporary covers to avoid ingress of water are mandatory.

· If the equipment is to re inspected, safety precautions are to be taken. Refer to Project Site Safety Procedures.

WP

Register to Reply
Guru
Safety - Hazmat - New Member Engineering Fields - Retired Engineers / Mentors - New Member Engineering Fields - Piping Design Engineering - New Member Hobbies - DIY Welding - New Member Fans of Old Computers - PDP 11 - New Member

Join Date: Feb 2007
Location: Stronger Than The Storm
Posts: 2394
Good Answers: 203
#23

Re: Nitrogen Purging to Prevent Internal Oxidation

10/29/2014 11:23 PM

As others have stated, both the potential customer, yourself and perhaps others in your firm need some remedial training on the fabrication, start-up and operation of gas pipe lines.

First, never pull a vacuum on a pipeline that will be used for pressure purposes. It wasn't designed for that and could possibly collapse part of the piping. It is much easier to collapse a pipe with a vacuum within it than it is to burst it with internal pressure.

If they insist on nitrogen purging consider the use of Dewar flasks of liquid nitrogen with an appropriate heat exchanger (similar to an automobile radiator). If you need more than those get a bulk trailer of liquid nitrogen and purge the pipe with the vapor from it. Cylinders would be very costly for the volume you are using. 2,800 m3 is a lot of anything. Estimate needing at least 5X the pipe volume for the gaseous nitrogen needed if direct purging is done.

In the USA the normal start-up for a new or extensively repaired gas pipe line is to have personnel enter the piping to clean out any garbage. Next flush the pipe with water to remove any materials within it. Close off all valves, etc., bleed off any air at the highest points, bring the pressure up to test pressure and disconnect the water supply. Wait for no drop in pressure. If pressure is not stable find the leak, repair it and start over again. For 24" to 42" pipe lines running at 1,000psi the test pressure is at least 1,200psi or the design test pressure.

After the test pressure has been held for the specified time: release the internal pressure, pump out the water, remove any line blocks (balloons), pump out all low spots and then pig the line to remove all water. This will take several to many runs of various pigs to clean it out and dry it.

Instead of purging the line with nitrogen directly I would suggest having the last pig run propelled by using a sealed rim pig and pressurize the line behind it with nitrogen to propel it. The nitrogen will replace the potentially moisture laden air with an inert atmosphere, the pigs will clean the interior of the piping and the pressure increased to the desired pressure, 10 psi. The pig can be removed at an appropriate removal point past the end of the pipe.

If you find it necessary to test the interior for rust or other materials a "cleaning pig" can be run through the line to remove and collect the materials. At any time another pig which checks for anomalies in the piping can be run and a report developed.

THIS IS NOT A PROCEDURE FOR COMPLETE PURGING OF A PIPE LINE WITH NITROGEN! It is only an overview of what can be done along with your consultant and codes. You and the customer are the ones that have responsibility for the pipe line, I don't. Get the necessary information and calculations from a very smart, and probably expensive, consultant with extensive experience with pipe lines.

Good Luck, Old Salt

__________________
Any day on the green side of the grass is a GREAT DAY!, --- me +++++++++. I believe creativity is an inherent part of everyone. --- Kermit T. Frog
Register to Reply Score 1 for Good Answer
Register to Reply 23 comments

Good Answers:

These comments received enough positive votes to make them "good answers".

"Almost" Good Answers:

Check out these comments that don't yet have enough votes to be "official" good answers and, if you agree with them, vote them!
Copy to Clipboard

Users who posted comments:

Crabtree (1); Fredski (3); IQ (3); kasharma (2); kevinm (1); lyn (5); old salt (1); redfred (2); Tom_Consulting (1); welderman (1); Whitephone (1); za.m171 (2)

Previous in Forum: Making Endless Woven Glass Fabrics   Next in Forum: Paint on Silicon Sealant

Advertisement