|
Perhaps one of the most common case failures studied by civil engineering students is the Hartford Civic Center Coliseum, which collapsed on January 18, 1978 at around 4:19 am. It is a valuable example of the consequences of bad design, poor project management and communication, and inadequate response to warnings signs.

The Incident
In 1970, engineers from Fraoli-Blum-Yesselman Associates began a project to design the proposed Hartford Civic Center Arena. The engineers came up with a unique roof frame design they called a space roof. The 300 by 360 ft. roof frame consisted of top and bottom square grids with joints 30 feet on center, connected by diagonal bars that caused staggered nodes on the top and bottom grid bars, resembling pyramid trusses when they were finished. This non-standard design was intended to save on costs and additionally provide some other features such as better drainage and the elimination of bending stresses.
The construction of this unique roof design was done entirely on the ground to save time and money. After being built, the frame was lifted into place using hydraulic jacks located on top of the four pylons of the building. The roof was completed in January of 1973 and the entire project sometime in 1975.
In 1978, Hartford experienced the biggest snowstorm of the roof's short five-year life. Only a few hours after a crowd of five thousand had left the Hartford Civic Center Coliseum, the roof of the building collapsed under the weight of the heavy snowfall. (Credit: LZA Investigation Report)
The Cause
The Hartford Civic Center's failure cannot be blamed on the weather. A three-member panel of organizations investigating the collapse found its cause to be due to three design problems:
· The top layer's exterior compression members on the east and the west faces were overloaded by 852%.
· The top layer's exterior compression members on the north and the south faces were overloaded by 213%.
· The top layer's interior compression members in the east-west direction were overloaded by 72%.
The design was, in short, extremely susceptible to buckling (the bowing of structural members under compression). Because the primary technical analysis was done by a computer program which did not account for buckling, the deficiency was never detected.
In addition, a number of omissions and detail discrepancies between the initial design and the actual construction significantly reduced the load capacity of the roof (as shown in the image below).

A lot of these design problems were detected during the construction and inspection of the roof, such as noticeable member deflections (while it was still on the ground and more easily fixable). Unfortunately, lapses in communication and poor decisions made by engineers ended in many of these issues and warnings being ignored or improperly fixed.
Lessons Learned?
Six years and $25 million in settlements later, I'm sure the engineers involved in the structure failure had "learned" their lesson. But in the college classroom, lessons from this incident have been learned time and time again by civil engineering students.
The Hartford Civic Center roof collapse is a great case study because it teaches about more than just buckling load. It provides important reminders of what is expected of engineers when working on a project. Most importantly, engineers need to be thorough in their work, especially in projects that impact a large number of people. Ethical and professional engineers are expected to have their designs adequately reviewed before construction, and they should not rely on computer programs to ensure the effectiveness of new or non-traditional approaches.
In addition, engineers need to take responsibility for problems that develop later in the process and be sure they are addressed properly. Good communication and organized project management are key to maintaining consistency, reducing errors, and preventing warning signs of bigger problems from being ignored.
Resource
Failure Wikispaces - Hartford Civic Center
|