The DC(a battery) test voltage is unknown but the procedure is to measure the earth terminal and farthest installation terminal so that the ohm-meter should not read more than 1 ohm.
If the installation is large each sub-circuit should be measured separately.
By definition, continuity testing requires the passing of a current to prove the continuity of the conductors.