HOW TO DECIDE SUBSTATION (MORE THAN 220 KV) CAPACITY IN ONE OND HALF BKR SCHEME HAVING 6 NO OF LINE BAYS , TWO NO OF ICT (200 mva , 400/132 KV) BAYS , 2 NUMBER OF 660mw GEN BAY AND ONE NUMBER BUS REACTOR BAY. (ANY STANDARD A/V FOR THE SAME CALCULATION)
ANY OTHER DETAIL REQUIRED MAY PL ASK .