The following actually happened and caused a debate between contractor, consultant and client. A high voltage substation was ready to be finally energized after several months of delay. The "problem" was the energization date is 24 months from the commissioning tests date. The client refused to have it energized unless all the tests are repeated for the transformers, HV switchgears and underground cables. The contractor refused. The consultant wants to repeat some tests only. Is the client, contractor or consultant correct? Is there an IEEE or IEC standard that says something about this issue?
Good Answers: