1- in the o-let branch connection, What is the size (with tolerance) of the opening in run pipe?
2- the attachement between the olet and the run pipe shall be full penetration grove weld?
3- deose the "full penetration groove weld" mean "complete fusion of the run pipe opening at the root pass"?